$1.25 Newsstand Price
Weekly Independent Local News
Friday, November 13, 2026

Burnham Street Update

BY VANESSA STARK

Construction is well ahead of schedule for the Burnham Street watermain repair in Lakefield.

Earlier this year, council approved starting work on the watermain replacement on Burnham Street. This work was originally scheduled for 2028, however staff felt there was an opportunity to begin work now, to coincide with work being done to rebuild the old Home Hardware location on Queen Street.

Over the last 10 years, there have been multiple watermain breaks along Burnham Street, specifically between Charlotte and Queen Street.

In 2024, during a valve replacement in the watermain, staff took the opportunity to fully inspect the watermain line and determined it to be in poor condition. From that inspection, it was determined that detail design and replacement should be considered in future budgets. These were then included in the 2025 Capital Budget.

However, in 2027 there is expected to be major roadwork done on the Lakefield Bridge repair which is expected to impact traffic. This could create logistical challenges and potential budget impacts on this project, the tender, and construction of the watermain replacement would be deferred until 2028 or beyond.

Over the last several weeks, the work on Burnham Street has been progressing quickly. Adam Tobin, manager of public works gave an update to council on the project during Tuesday afternoon’s council meeting.

He recommended increasing the work being done in the area due to the scheduling. This would complete the work that was originally set to be completed in 2028, reducing disruption on businesses and residents.

In his report, Tobin stated that the construction team is currently two weeks ahead of schedule. Because of this he recommended that the scope of the project be expanded to include replacement of the remaining section of the watermain along Burnham Street, extending south to Water Street.

His report said that it is expected that the contractor could complete the additional proposed work with minimal impact on the overall schedule. Completing the work this year would see savings on future costs that would be incurred from mobilization/demobilization and inflationary increases.

Once Home Hardware construction is completed, the final lift of asphalt can be placed over the full extent of Burnham Street.

Originally, the cost of the project was estimated at about $230,000 and was recommended to be funded through the Lakefield Water Reserve.  The additional work would be an added $430,000 to this cost, however overall, it is expected to save costs in the long run from inflation costs as well as have the least long-term impact on residents.

The recommendation was approved by council.